DDA Revises 'How the West was One' Update

The water shutdown schedule for the West Nine Mile Road reconstruction project in Ferndale has been tweaked.

Editor's note: The Ferndale Downtown Development Authority on Monday revised its update on the "How the West was One" reconstruction project along West Nine Mile Road for the week of May 20. The revised update follows.

[Click here to read the DDA's original update for the week of May 20.]

The good news is that the contractors have been able to progress quickly on the water main project, and they are taking the businesses concerns and issues with water shutdowns seriously. In light of this, the contractors' plans have changed for this week of May 20th for water connections.

Interested in local real estate?Subscribe to Patch's new newsletter to be the first to know about open houses, new listings and more.

The water shutdowns will still occur either Thursday and/or Friday this week  for the following:

  • Residents on Kenton
  • Residents on Beaufield
  • Dairy Queen (their service feeds off of Kenton St., not Nine Mile)

Water connections can take up to 4 hours. All other businesses will not be affected by a shut down.

Interested in local real estate?Subscribe to Patch's new newsletter to be the first to know about open houses, new listings and more.

Service reconnections for businesses along Nine Mile will occur the week of May 28th, which only take about 1/2hr.

Also note: there was a water main break earlier this morning, but the situation was handled quickly and efficiently. The only business affected by this brief shutdown (@1hr.) was Courtesy Cleaners. 

If you have any questions, please don't hesitate to call the DDA at 248-546-1632. We are here to inform and help!

Source: Ferndale Downtown Development Authority